REPRESENTATIVE

CLIENT DAEWOO LOGISTICS / SUNGJIN GEOTECH
BUSINESS NAME EVAPORATOR 2 SET SEA TRANSPORT
CONSTRUCTION SCALE 2011/11 ~ 2012/02
CONSTRUCTION PERIOD 2011/11 ~ 2012/02
BUSINESS INFORMATION

1) REVIEW OF DESALINATION EQUIPMENT LOADING AND UNLOADING PLAN


2) SEA TRANSPORT STABILITY REVIEW


3) SEA FASTENING TECHNOLOGY REVIEW AND PLAN PREPARATION


4) SEA FASTENING STRUCTURE DESIGN


5) SHIPPING SUPERVISION

SUB PERFORMANCE

NO. CLIENT BUSINESS NAME CONSTRUCTION PERIOD BUSINESS INFORMATION PHOTO DETAILS
1 GLOBAL / SEJIN HEAVY INDUSTRIES / HYUNDAI HEAVY INDUSTRIES FLARE TOWER SEA SHIPPING 2013/03 ~ 2014/10

1) FLARE TOWER BLOCK INLAND TRANSFER ENGINEERING

2) FLARE TOWER SEA TRANSPORTATION ENGINEERING

3) LOAD OUT & SEA FASTENING

2 GS E&C NO.3 HOU PROJECT MODULE SEA TRANSPORT 2008/07 ~ 2008/09

1) MODULE STRUCTURE ANALYSIS

2) LOADING BEAM DESIGN FOR MODULE TRANSPORTATION

3) DESIGN FOR SHIPPING BY SEA

4) TECHNICAL SUPPORT SERVICE

3 DOOSAN HEAVY INDUSTRIES & CONSTRUCTION / DONGBANG POSCO CSU MARINE TRANSPORTATION 2003/08 ~ 2004/05

1) REVIEW OF CSU LOADING AND UNLOADING PLAN

2) SEA TRANSPORT STABILITY REVIEW

3) SEA FASTENING TECHNOLOGY REVIEW AND PLAN PREPARATION

4) SEA FASTENING STRUCTURE DESIGN

5) LOADING AND UNLOADING SUPERVISION

4 GS E&C / PERTAMINA RFCC SEMI MODULE SEA TRANSPORT 2012/10 ~ 2014/01

1) RX & RG STRUCTURE SEMI MODULE HANDLING
   ENGINEERING

2) ASSEMBLY AREA LAY OUT ENGINEERING

3) SEA TRANSPORTATION ENGINEERING

4) LIFTING & ERECTION ENGINEERING

5) 3D CLASH CHECK

5 DAEWOO LOGISTICS PARADIP REFINERY PROJECT PRESSURE VESSEL SEA TRANSPORT 2011/01 ~ 2011/09

1) SEA TRANSPORTATION ENGINEERING

6 HYUNDAI E&C LAUNCHING GANTRY OCEAN SHIPPING 2018/04

1) LIFTING ENGINEERING

2) SEA TRANSPORTATION ENGINEERING

7 SAMHWAN ENTERPRISE / SUNGCHANG INDUSTRIAL GWANGAN BRIDGE SECTION 2 SUSPENSION BRIDGE TEMPORARY CONSTRUCTION TRUSS MARITIME TRANSPORTATION 2001/07 ~ 2002/04

1) REVIEW OF TRANSPORT EQUIPMENT

2) SEA FASTENING DESIGN

3) LOADING AND UNLOADING DESIGN

4) REVIEW OF THE GROUND ASSEMBLY METHOD

8 HUTA / ASAN INTERNATIONAL 1200TON CLASS FLOATING CRANE SEA TRANSPORT 2011/03 ~ 2011/06

1) BOOM STRUCTURAL STRENGTH ANALYSIS AND REPORT PREPARATION ACCORDING TO THE SELF-PROPELLED SHIP’S MOTION

2) DRAWING OF BOOM SEA FASTENING ACCORDING TO ANALYSIS RESULT

3) DRAWING AND REPORT OF SEA FASTENING OF GENERAL EQUIPMENT

9 GLOBAL / SAMSUNG HEAVY INDUSTRIES / STATOIL STAIR TOWER SEA TRANSPORT 2017/11 ~ 2018/04

1) STAIR TOWER (ALUMINUM) SEA TRANSPORT ENGINEERING

10 SAMSUNG HEAVY INDUSTRIES ICHTHYS BLOCK SEA TRANSPORT 2014/01 ~ 2014/09

1) ICHTHYS BLOCK LIFTING ENGINEERING

2) SEA TRANSPORTATION ENGINEERING

11 DAEWOO E&C / SUNGCHANG INDUSTRIAL SEOSAN ARRIVAL AND SHIPMENT PIER CONSTRUCTION JACKET MARINE TRANSPORTATION 2004/05 ~ 2005/12

1) JACKET SHOP DRAWING

2) CUTTING PLAN

3) SEA FASTENING ENGINEERING

4) STRUCTURE ANALYSIS

12 DAEWOO E&C / SUNGCHANG INDUSTRIAL GWANGYANG LNG TERMINAL JACKET MARINE TRANSPORTATION 2003/06 ~ 2004/09

1) SHIPMENT METHOD AND SHIPPING EQUIPMENT LAYOUT PLAN

2) STOWAGE PLAN & STABILITY REVIEW

3) SEA FASTENING DESIGN

4) STRUCTURAL CALCULATION AND STABILITY REVIEW

13 DOOSAN HEAVY INDUSTRIES & CONSTRUCTION FUJAIRAH HRSG PROJECT MODULE / DUCT SEA TRANSPORT 2001/10 ~ 2002/01

1) MODULE & DUCT STRUCTURE ANALYSIS

2) SEA FASTENING DESIGN

3) REVIEW OF SHIPPING VESSELS

4) SUPERVISION